Chengdu Tram Line 2 is a tram line in Chengdu, China. The line has a total length of 39.3 kilometres (24.4 mi) and 35 stations (and will have 47 in the long term). It has a 'Y' layout and runs from the Chengdu West railway station to Pixian West railway station and Hongguang.[1] The line was officially started in December 2015, and the 13.7 km (8.5 mi) demonstration section of the line was opened on 26 December 2018,[2][3] and the remaining sections were opened on 27 December 2019.[4]

History

In 2014, Chengdu disclosed the concept of building a modern tram system in the first and second round of rail transit planning. The construction concept of Chengdu Modern Tram System was disclosed in 2014. In September 2015, Chengdu Development and Reform Commission formally issued an agreement to Chengdu IT Avenue Modern Tram with the document "Chengfa Reform Government Approval [2015] No. 216". Route 2 line approval,[5] the same month, the Chengdu Municipal government announced the "urban rail transit network construction to speed up the implementation of the program."

The line started the preliminary construction in December 2015. On 15 April 2016, the proposed naming of the 47 stations on the Chengdu route 2 entered the publicity stage and was approved by the Chengdu Municipal Government in July of the same year. In September 2016, the entire line started construction and the line demonstration site Baiye Road Station was completed in December. In June 2017, Chengdu CRRC Long Passenger Rail Vehicle Company announced the low-floor tram vehicles used on the line.[6] On 25 September of the same year, the first section of the line achieved long-track rail connection, and it was announced that it would open in the first half of 2018.[7]

On 25 January 2018, the first section of the line was energized by the contact network; on August 10, the line completed the "hot slip" test; on September 6, the line was handed over to the operating unit; on September 10, the line started the EMU commissioning work; At the beginning of December, the installation of traffic safety signs for the first opening section was completed. On 26 December 2018, the first section opened for trial operation. On 26 December 2019, the non-initial segment opened.

Timeline

Tram route

Practical Info

The main line of Chengdu Tram Line T2 runs from 07:00-20:40 (to Chengdu West railway station) / 07:00-21:00 (to Pixian West railway station), and the branch line runs from 07:00-20:50 (to Xinye Road)/07:00-21:30 (toward Chenguang), the departure interval is about 10 minutes, and the whole journey takes about 40 minutes.

Fleet

Tram at Chengdu West railway station
interior view of a tram

The Chengdu Tram Line 2 train has three colors of blue-green, light blue and bright yellow. It adopts the Alstom Citadis 302 technology platform 100% low-floor 5-module steel-wheeled tram, 32.6 m (106 ft 11 in) long and 2.65 m (8 ft 8 in) wide, manufactured in Chengdu's CRRC Changchun Railway Vehicles plant. The tram has 64 seats, a capacity of 300 people, and a maximum passenger capacity of 380 people. The average speed of the tram is 23 km/h (14 mph), the maximum speed is 70 km/h (43 mph), the maximum gradient is 60‰, and the minimum turning radius is 20 m (65 ft 7 in),[8] vehicles uses a combination of super capacitor and ordinary catenary power supply to ensure the power when passing through some intersections. The car is equipped with barrier-free facilities and a button to open the door.[9]

Theme tram

When the Chengdu route 2 was fully opened in 2019, a theme tram with the theme of "National Security Archives" went online simultaneously. The painting of the tram is based on the theme of spring, summer, autumn and winter, and nine nationally protected animals are interspersed in the form of illustrations, and corresponding science content is set in the car, calling on citizens to pay attention to and participate in the protection of endangered wild animals.

Termini are Chengdu West railway station, Pixian West railway station & Renhe.

Alignment and Interchanges

Chengdu Tram Line 2 has a total length of 39.3 km (24.4 mi), of which the elevated section is 1.8 km (1.1 mi) and the ground section is 37.5 km (23.3 mi). Chengdu Tram Line 2 leads from Chengdu West Railway Station, heading northwest to Xinye Road Station, and then along two lines to Pixian West railway station and Renhe. In addition, in 2018, the newly planned Honggao branch line of Chengdu Line 2 leads from Hezuo Road Station to Jintu Station, connecting the Xipi section and the Xinhong section, making the whole line a ring.

Chengdu tram platform

The platform of Chengdu Tram Line 2 is open, and passengers must purchase tickets or swipe cards on the train. The platforms of the first section are all side platforms, and are equipped with half-height screen doors (not in use), seats and train information display screens. The platforms on both sides are not symmetrical and do not communicate directly. For the sake of cost saving and easy maintenance, the subsequent stations did not install half-height screen doors, and replaced the tempered glass railings with wire mesh materials.

Tickets

The fare of the line is two yuan for the whole journey, which is paid by cash or Tianfutong, and supports Tianfutong, Cloud QuickPass or the application of two-dimensional code scanning in Chengdu Metro.

See also

References

  1. ^ 江瑶 (28 September 2016). "成都有轨电车蓉2号线全线加速建设 2018年通车". 四川新闻网. Archived from the original on 29 December 2017.
  2. ^ "我国西南地区首条有轨电车线路开通运营". 26 December 2018. Archived from the original on 9 November 2019.
  3. ^ 尹沁彤 (16 August 2017). "成都有轨电车蓉2号线2018年开通观光体验段". 成都商报. Archived from the original on 29 December 2017.
  4. ^ "成都地铁5号线等3条线路今年底将开通试运营". 17 October 2019. Archived from the original on 18 October 2019.
  5. ^ 张舒 (14 September 2015). "成都IT大道有轨电车正式获批立项 年底前将开工". 成都商报. Retrieved 29 December 2017.
  6. ^ 刘忠俊 (15 June 2017). "成都首条有轨电车机车组亮相". 中新社. Retrieved 29 December 2017.
  7. ^ 廖雪芝 (26 September 2017). "有轨电车蓉2号线首开段轨通 预计明年上半年试运营". 成都晚报. Retrieved 29 December 2017.
  8. ^ "成都日报:快看!成都首列现代有轨电车 昨日正式下线 最多可载客380人 最高时速可达70公里-成都地铁". www.cdmetro.cn. Archived from the original on 6 June 2017. Retrieved 7 September 2017.
  9. ^ "首条有轨电车蓉2号列车下线 明年乘电车看风景". 成都晚报. 31 May 2017. Archived from the original on 6 June 2017.