Expressway S3 or express road S3 (in Polish droga ekspresowa S3) is a Polish highway, which is planned to run from Świnoujście on the Baltic Sea through Szczecin, Gorzów Wielkopolski, Zielona Góra and Legnica, to the border with the Czech Republic, where it will connect to the planned D11 motorway. The total intended length is 470.6 km (292.4 mi), of which 436.0 km (270.9 mi) is open to traffic and 33.0 km (20.5 mi) is under construction as of August 2024.

The main section from Szczecin (interchange with A6) to the Czech border is completed. In was constructed from 2008 until 2024. The last 3 km near the border remain closed to traffic until around 2028 when the connecting stretch of the D11 motorway is to be constructed in Czech Republic.

The section from Świnoujście to Szczecin (A6) is partially completed and partially under construction, with planned completion by the end of 2024.[2]

Route

History

Initial route plans (autostrada A3)

The autostrada A3 was a motorway planned from 1993[3][4] to 2001[5] that was supposed to run from Szczecin to Lubawka on the Polish-Czech border. Some road maps published in the 1990s depicted an approximate route of the motorway, which in some places was different from the final route of S3, most notably the motorway was supposed to form north-eastern bypass of Legnica[6] while S3 was constructed as its western bypass.

In 2001 the decision was made to build a lower standard "express road" as the traffic density was judged too low to justify a motorway.[7] One legacy of the road having been planned as an autostrada is that from the beginning it was being constructed on a completely new alignment some distance away from the old route of the DK3 road. This is akin to how most expressways in Poland are constructed nowadays, but in contrast to the standards of the 2000s when most of the expressways were being constructed by upgrading existing roads. Like other modern Polish expressways, S3 shares the crucial properties of an autostrada, including physical separation, restricted access, all interchanges being grade-separated, and at least two continuous lanes in each direction as well as emergency lanes (hard shoulder).

Świnoujście – Szczecin

One section of S3 east of Szczecin (19 km) was constructed in the 1970s in an expressway standard of those times, featuring one-level intersections and a pedestrian crossing. It was reconstructed in 2019–2020 to contemporary standards, with the intersections and the pedestrian crossing upgraded to grade-separated ones.

S3 south of Szczecin overlaps with A6 motorway (see Autostrada A6: History of construction).

Szczecin – Legnica

A single carriageway was constructed in years 1985–1995 on the section Sulechów–Zielona Góra (27 km). Three short sections were constructed in years 2001–2008, also with the first carriageway only.

The first large section of S3 was the stretch from Szczecin to Gorzów Wielkopolski (82 km), opened to traffic in 2010,[8] followed by the stretch from Gorzów Wielkopolski to Sulechów (80.6 km), opened to traffic in 2013/2014. The new sections had two carriageways, separated by the older stretches (Sulechów–Nowa Sól, Gorzów Wielkopolski bypass and Międzyrzecz bypass) which still remained as single-carriageway.

In 2014–2017/2018, the expressway between Nowa Sól and Legnica (junction with A4) was constructed, and the second carriageway was added on the three older stretches.[9] The exception was the section Polkowice - Lubin, which was also contracted to be completed in the first half of 2018, but the deal with Salini Impregilo was terminated in 2019 due to extensive delays in construction. It was ultimately opened to traffic in 2021.

Legnica – border with Czech Republic

Signing the contracts for construction of all four stretches between A4 at Legnica and the Czech border was planned for 2014. However, in 2013 the officials announced that the section will not enter into construction yet, because delays in preparations in the Czech Republic meant that the connecting motorway on the Czech side of the border might enter into construction no earlier than 2018[10][11] (ultimately, the delays on the Czech side turned out to be even larger and the construction of the connecting stretch is expected to start in 2024 rather than in 2018[12]). Some of the money allocated for it has been re-purposed to build the S2 expressway in Warsaw.

Later the decision was partially reversed, and in 2014 two tenders were opened for the section between Legnica and Bolków. This part (35.8 km) was constructed in years 2015–2018.[13] The two remaining design-build contracts for the section from Bolków to the Czech border were signed in October 2018. The section from Kamienna Góra to the border was opened in September 2023, while the section from Bolków to Kamienna Góra was opened in July 2024.

Exit List

References

  1. ^ Of these 18.3 km shared with A6 motorway.
  2. ^ Uchwała RM nr 108/2019
  3. ^ Rozporządzenie Rady Ministrów z dnia 28 września 1993 r. w sprawie ustalenia kierunkowego układu autostrad i dróg ekspresowych [Decree of the Council of Ministers on September 28, 1993 on establishing a directional arrangement of motorways and expressways], Dz. U., 1993, vol. 92, No. 424
  4. ^ "Map of planned network of motorways and expressways in Poland in 1993". Archived from the original on 13 January 2014.
  5. ^ Rozporządzenie Rady Ministrów z dnia 29 września 2001 r. w sprawie ustalenia sieci autostrad, dróg ekspresowych oraz dróg o znaczeniu obronnym [Decree of the Council of Ministers on September 29, 2001 on establishing a network of motorways, expressways and roads of defensive importance], Dz. U., 2001, vol. 120, No. 1283
  6. ^ Mapa samochodowa Polski 1:700 000 [Road map of Poland 1:700 000] (in Polish). Szczecin: Wydawnictwo Kartograficzne KOMPAS. 1996–1997. ISBN 83-904373-2-5.
  7. ^ "Rozporządzenie Rady Ministrów z dnia 29 września 2001 r. w sprawie ustalenia sieci autostrad, dróg ekspresowych oraz dróg o znaczeniu obronnym".
  8. ^ "www.gddkia.gov.pl". Archived from the original on 2010-10-27. Retrieved 2010-10-22.
  9. ^ "Budimex, Mirbud and Mostostal Warszawa bid in tender for S3 ring road | the Best in Poland". Archived from the original on 2013-12-03. Retrieved 2013-11-23.
  10. ^ Poludniowa_obwodnica_Warszawy_zamiast_ekspresowki.html Południowa obwodnica Warszawy zamiast trasy S3 do Czech, Gazeta Wyborcza, Dec. 9, 2013
  11. ^ "Zamiast S3 będzie obwodnica Warszawy. Rząd zabrał nam pieniądze, a winą obarcza... Czechów". 17 October 2013.
  12. ^ "Revize slibů ministrů za ANO. D11 do Polska bude hotová o čtyři roky později, než sliboval Ťok". 20 November 2019.
  13. ^ "Polish Council of Ministers decision from March 4, 2014" (PDF). Archived from the original (PDF) on March 26, 2014. Retrieved March 26, 2014.